Building Central Asia's
first Tier IV data fortress.
We update the world on every phase — from foundation to certification. 11 hectares of purpose-built infrastructure under construction in Astana.
Live from the campus
Real-time camera feed from the Astana construction site.
Connecting to the live camera…
Foundation complete. First buildings rising. Pipeline 107% filled.
- Campus area
- 11 hectares
- Total build area
- 60,000 m²
- DC buildings
- 4
- IT load (phase 1)
- 5.28 MW
- First-phase launch
- May 2027
- Pipeline
- 107%
Project timeline
- Oct 2025
Land preparation complete
Site grading, access roads, and utility tie-ins finalized on the 11-hectare Astana campus.
- Nov 2025
Foundation poured
Reinforced concrete foundation laid for the first DC building.
- Dec 2025
Structural erection
Primary structural steel and envelope going up on building 1.
- Jan 2026
TCDD (design documents)
Uptime Institute lists AKASHI Data Center 1, Phase 1 with Tier IV TCDD. Design certified — not the built hall. TCDD is not TCCF.
- Feb 2027
MEP rough-in
Cooling headers, power distribution, and fire suppression being installed.
- Mar 2027
Commissioning works
Comprehensive testing and tuning of all engineering systems before DC handover.
- Apr 2027
TCCF constructed-facility audit
Uptime Institute on-site audit of the built facility (TCCF). Separate from TCDD.
- May 2027
First phase soft-launch
Initial server halls handover to anchor tenants.
- 2027+
Expansion to 100 MW
Additional DC buildings come online. Full 4,224-rack capacity.